Stadium construction works Roberto Mariano Bula de Colón They are slow and have more than 60% progress, explained L.uis Denis Arce, director of Pandeportes and where you expect the company to fulfill the contract.
“We must recognize that there are ongoing projects, that the intention is to complete them and we invite companies to Pandeportes, apply the obligation that exists in the contract, as is the case with the stadium Mariano Bula, Rico Cedeño in Chitré, Herrera Combat Center and others Veraguas el Toco Castillo'”, dArce said, adding, “We will be at the top of the companies to be able to achieve this.”
On his part, Luis Marín, regional director of Pandeportes de Colón, reported that it can be seen that the works being carried out on the stadium are 63 percent complete, but the works are going slowly, so they are trying to get the company to speed up the works.
The company maintains a minimum workforce, so the schedule is not followed, he added.
Work is currently being carried out on the construction front, which includes blocking, masonry and plastering, the lower part of the stands, the electrical installation front which is already about 90% finished, and the fire protection system is almost ready.
“We want to speed up the preparation of the field, the parking lots that are 70 percent complete, the installation of prefab stands that are already 90 percent on the field,” he added. Marin.
He also pointed out that all lighting equipment is available on the field. ICE which will be used, light towers, panels, he expressed.